Mooring boats
|
|
- Vessels transiting the Canal must have
mooring boats as mentioned hereafter hired from the Suez
Canal Mooring Company approved by SCA in case no mooring
boats from the said company are available , ship's boats if
suitable for mooring ( open type life boat ) in the canal
can be used and must be manned by shore crew , hired from
the SC mooring company , each boat is to be manned by three
men.
- One mooring boat or one motor boat for
vessels under 2500 tones gross SC.G.T
- One motor for vessels from 2500 to 5000
tons gross , SC G.T
- Two motor boats or one motor boat and one
mooring boat for vessels from 5000 SC G.T to 30000 SC G.T
- Two motor boats for vessels over 30000
tons gross , SC.G.T
- Ships may ask for additional motor boats
or mooring boats according to Master 's request
These mooring boats must be in constant readiness for
lowering to run the ropes to the mooring posts without any
delay during the transit of vessel
- Ships must be fitted with well maintained
lifting appliance capable of lifting mooring boats of 4 tons
weight ( Including crew members )
- Ships may carry extra mooring boats as
passengers for the interest of navigation. However L.P.G ,
L.N.G and loaded Tankers are not allowed any extra boats.
- The handling of mooring boats must be
carried out well clear from the ship's propellers.
- Master are requested to reduce speed
during lifting or lowering operations of mooring boats , an
officer must be in charge , to avoid accidents that may
endanger the life of mooring men
- If the vessel has no means for lifting
mooring boats and ship's boats are not suitable for mooring
in the Canal , the vessel shall not be allowed to transit
the Canal.
|